bwb-logo-white

Ledbury STW – Phosphorus Removal

Project Description

Ledbury STW is a medium size activated sludge plant in Herefordshire, treating domestic sewage and trade effluent from a brewery. The current total population equivalent (PE) is over 14,000, and expected to approach 20,000 in 2028.

In AMP6, under the Water Framework Directive (WFD), the site had to meet more stringent discharge standards, including tightening the total phosphorus (TP) consent from 2 mg/l to 0.3 mg/l, with an Iron consent of 4 mg/l.

To achieve these new consent standards, Costain (Severn Trent’s main contractor) installed a chemical dosing facility and a FilterClear® plant.

The decision was based on a comprehensive whole life cost (WLC) assessment of various tertiary solids removal (TSR) plants.

The FilterClear® skid was assembled and hydraulically tested off-site at Bluewater’s works, before being transported to site for installation on a flat concrete slab.

Project Name:Ledbury STW
Client:Severn Trent
Capacity:160 L/s
Main Contractor:CiM6
Project Scope:Design, supply
& commission

Project Highlights

• Off-site manufacture

• Consent of 0.3 mg/l TP and 4 mg/l Fe

• Rapid installation and commissioning

• No separate flocculation tank needed

Scope of Works

Design, procurement, manufacture, installation and commissioning of Bluewater Bio’s proprietary FilterClear® 4v2800 plant. Fully automated and instrumented tertiary filtration system for Total Phosphorus removal.

Project Duration

FilterClear delivered: February 2020

Installation time ~ 5 days

Commissioning time ~ 6 days

Compliant by: March 2020

Client Contact

Client organisation: Severn Trent

Contact person: Derick James (Project Manager)

Ledbury STW Process Parameters

Average flow192 m3/h
Maximum flow578 m3/h (160 l/s)
Design Influent TSS conc.
(incl. chemical solids)
32 mg/L (average)
43 mg/L (98%ile)
Effluent TP consent0.3 mg/L (average)
Effluent Fe consent4 mg/L (95%ile)

“The HYBACS upgrade at Tubli alleviates the current overloading problem without the requirement for green-field construction, thereby utilising the existing secondary treatment assets whilst avoiding additional land take. Early results demonstrate that the plant is operating exceptionally well and meeting the highest standards, with an overall improvement in Nitrogen removal of 80%”.

Share the Post:

Related Case Studies

Bolsover STW Phosphorus Removal

The FilterClear installation at Bolsover forms part of the national CIP program, to ascertain the feasibility and real costs associated with achieving low (0.5 mg/L) to ultralow (0.1 mg/L) total phosphorus consents.

Read More

HYBACS Upgrade at Tsakane WwTW

Following rapid catchment growth, East Rand Water Company(ERWAT) required an upgrade from 10 MLD to 20 MLD at its Tsakane WwTW. The existing works comprised a single biological nutrient removal (BNR) reactor which could not be taken out of service for long periods of time.

Read More

Jubail HYBACS Upgrade at IWTP-8

Industrial Wastewater Treatment Plant no.8 (IWTP8) treats effluent from most of the industrial area in the city of Jubail, Saudi Arabia. The plant comprises three parallel streams; stream 2 was based on the activated sludge process and treated around 25 MLD to the Saudi RCER-1999 Irrigation Water standard.

Read More

Contact Our
NeoTech Team

Please complete the form and one of our technology team will get back in touch with you as soon as possible:

Contact Our
CFIC® Team

Please complete the form and one of our technology team will get back in touch with you as soon as possible:

Contact Our
HYBACS® Team

Please complete the form and one of our technology team will get back in touch with you as soon as possible:

Contact Our Team

Please complete the form with as much detail as possible about your project and one of our technology team will get back in touch with you as soon as possible:

Contact Our
FilterClear® Team

Please complete the form and one of our technology team will get back in touch with you as soon as possible: